RAILWAY ELECTRIFICATION

Sl. No

Details of Work

Year of sanction

Original sanctioned Pink book cost

Latest Anticipated/ Sanctioned Cost

Cum.Exp. Up to  30.06.2015

Physical progress

32

Dharmavaram—Yelahanka Electrification (214 Km) as part of Gooty-Dharmavaram-Yelahanka Electrification project (304 Km)

2010-11

136.30 Cr.

(Total cost Rs.193.69 Cr for the entire project)

161 Cr.

(Total cost Rs.229 Cr for the entire project)

176 Cr. (Total Rs.250.17 Cr for Gooty-Dhamaravaram-Yelahanka)

85%

Status:

(i) Work being executed by RVNL. Erection of OHE Masts and wiring has been completed in the entire section from Yelahanka to Dharmavaram. 

(ii) Works of construction of Traction sub-station and switching stations is in progress. 


Target:-  March, 2016.


Sl. No

Details of Work

Year of sanction

Original sanctioned Pink book cost

Latest Anticipated/ Sanctioned Cost

Cum.Exp. Up to  30.06.2015

Physical progress

33

 Hospet-Bellary-Haddinagundu (92 km) as part of Hospet-Bellary-Guntakal Railway Electrification (138 km)

2012-13

123 Cr.

(Total cost Rs.185 Cr  for the entire project.)

151 Cr.

(Total cost Rs.226.68 Cr  for the entire project.)

-

-


Ø Detailed Estimate at Rs.226.68 Cr for the entire Project (Rs.151 Cr from for section falling in SWR) was sanctioned in the year 2013.  Project being executed by RVNL

Status:  Tenders are under evaluation and finalization.  Project targeted for completion by March, 2018.




Source : South Western Railway CMS Team Last Reviewed on: 06-10-2015