Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/ FM 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

DLPB-30

 

Birur-Shivani(28.67 Km)

2010-11

142.64

154.34

2.00/ 1.40

1.49/ 155.83

100%

Remarks:-

Project has been completed and commissioned.

 




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018