Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/ RE

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NL

PB-1

 

Kottur-Harihar

(65kms)

1995-96

488.70

Cost sharing2/3: 1/3 between GoK & Rly

427.13

8.00/ 11.50

4.50/ 431.63

95%

Remarks: - Section completed and commissioned (65 Kms) on 03.03.2014 on “One Train System only”.Section is commissioned on “Absolute Block System” of working on 30.05.2016.

 




Source : South Western Railway CMS Team Last Reviewed on: 17-01-2018  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.