PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

NL

Kolar-Mulbagal-Madaghatta NL (45 km)

2012-13

209.35

0.04

5.00

0.56/ 0.60

Nil

Remarks:-

Land acquisition proposals for entire required land have been submitted to GoK and land is yet to be acquired.State Govt. has entrusted land acquisition to KIADB.  Revenue survey has been completed by KIADB.

 