PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/FM 2017-18

Exp. Up tothe month/ Cum. exp

Physical progress

NLPB-9

Whitefield-Kolar (52.9 km)

2011-12

348.85

On 50:50 cost sharing basis and land free of cost by GoK

0.35

0.50/ 0.00

0.00/

0.35

Nil

Remarks:-

 

Work yet to start for want of land.

 




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018