PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/FM

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NLPB-3 SC Rly

Munirabad

(Ginigera)-Raichur(165 km)

2007-08

1350.91

Cost sharing on 50: 50 basis between GoK &Rly.

694.79

145.00/ 45.50

120.86/ 

815.65

27%

Remarks:-

 

Section between Ginigera-Chikkabenakal (27 km) commissioned on 31.03.2017 for passenger traffic.  Further work are in progress in Chikkabenakal (Km 27)-Gangavathi (Km 40)- Karatagi (Km 68) section.




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018  


  SWR Personnel-Web Mail | Admin Login | Site Map | Contact Us | RTI | Disclaimer | Terms & Conditions | Privacy Policy Valid CSS! Valid XHTML 1.0 Strict

© 2016  All Rights Reserved.

This is the Portal of Indian Railways, developed with an objective to enable a single window access to information and services being provided by the various Indian Railways entities. The content in this Portal is the result of a collaborative effort of various Indian Railways Entities and Departments Maintained by CRIS, Ministry of Railways, Government of India.