PROGRESS OF WORKS FOR THE MONTH OF
FEB.2018

Cate-gory

Details of Work

Year of sanction

Anticipated /Sanctioned Cost

Cum. Exp. Up to March 2017

BG/FM

2017-18

Exp. Up tothe month/ Cum. Exp.

Physical progress

NLPB-3 SC Rly

Munirabad

(Ginigera)-Raichur(165 km)

2007-08

1350.91

Cost sharing on 50: 50 basis between GoK &Rly.

694.79

145.00/ 45.50

120.86/ 

815.65

27%

Remarks:-

 

Section between Ginigera-Chikkabenakal (27 km) commissioned on 31.03.2017 for passenger traffic.  Further work are in progress in Chikkabenakal (Km 27)-Gangavathi (Km 40)- Karatagi (Km 68) section.




Source : South Western Railway CMS Team Last Reviewed on: 13-03-2018