Financial Summary of Projects
|
SUMMARY OF CONSTRUCTION PROJECTS ON HAND (in crore)
| Type of Project | No of projects | Sanctioned length in kms | Length completed in Km | Total Anticipated cost | Exp up to Mar 2012 | Likely Exp. up to Mar 2013 | Throw forward | Balance funds requirement |
| |
| | SWR | GOK/ | SWR | GOK/ |
| | GoAP | GoAP |
| | NL | 12 | 1627 | 155 | 6910 | 2250 | 1191 | 1486 | 7919 | 4751 | 3168 |
| | 245 |
| | GC | 5 | 643 | 606 | 1363 | 298 | 1112 | 1195 | 465 | 191 | 274 |
| | DL | 13 | 752 | 211 | 3955 | 351 | 948 | 1264 | 3043 | 2860 | 183 |
| | Total | 30 | 3022 | 972 | 12228 | 3144 | 3251 | 3946 | 11427 | 7802 | 3625 |
| | Average yearly expenditure / outlay works out to Rs.384 cr. (Average of last 3 years) |
| | Total Throw forward is Rs.11427 cr. |
|
Source : South Western Railway CMS Team Last Reviewed on: 04-07-2012
|
|
|